PLN tests network for 14 households in Tugasoki, Ende
PLN UP2K Flores completed a commissioning test for a 0,74-kilometre low-voltage network in Tugasoki hamlet, Ende, intended for 14 prospective customer households.
· 1 min read
Ende — PT PLN (Persero) UP2K Flores completed a commissioning test on Thursday, 22 October 2026, for a 0,74-kilometre low-voltage network in Dusun Tugasoki, Ekoae Village, Wewaria subdistrict, Ende Regency. The test is intended to support electricity access for 14 prospective customer households in the hamlet.
The work concerns a Jaringan Tegangan Rendah (JTR), or low-voltage electricity network. The commissioning test checks whether the network is ready to operate safely and reliably before service is extended to prospective customers. The network measures 0,74 kilometre and is intended for 14 households.
Why it matters to readers
The project would bring grid infrastructure to a rural hamlet in Ende and could improve access to electricity for 14 households. The location is in Flores, where PLN has continued developing village and hamlet networks. The test marks the completion of the commissioning process for the network in Dusun Tugasoki.
The network serves Dusun Tugasoki in Ekoae Village, within Wewaria, Ende. PLN UP2K Flores is the project unit. The commissioning test took place on Thursday, 22 October 2026, before electricity service is extended to the 14 prospective customer households.
Sources
Read next
More on this story

Islands & Spots
D'Ende Hill Cafe opens new city-view venue in Ende
D'Ende Hill Cafe and Resto opened in Ende on 9 October 2026. The family restaurant is located at Kaki Lena and offers dining with views of the city la…
Latest in Flores & Beyond

Related