Five of 458 planned temporary shelters in Manggarai Barat were complete by 15 November 2026, while six more exceeded 50% progress, according to BNPB’s local representative.
· 2 min read
Manggarai Barat — On 15 November 2026, BNPB’s person responsible for Manggarai Barat, Hadi Sutrisno, said five of 458 planned temporary shelter units had been completed in the regency.
Why it matters: Residents affected by the 15 August earthquake were still waiting for most of the 458 planned temporary shelters, with completion targeted for December.
The five completed units represented 1.1% of the target. Four were in Boleng and one in Welak, with one built independently by a survivor and eligible for reimbursement subject to local technical assessment, according to Floresa.
Hadi said six additional units were more than 50% complete: two in Boleng, one in Komodo and three in Lembor. Twenty-one others were below 50% completion, including four in Boleng and 17 in Lembor.
Construction had not begun in seven other districts—Kuwus, Kuwus Barat, Ndoso, Macang Pacar, Pacar, Sano Nggoang and Mbeliling—although some were preparing materials and workers, Floresa reported.
The temporary shelters are part of the response to the magnitude 7.7 earthquake that struck Flores on 15 August 2026. A field report published through ReliefWeb said the earthquake affected Manggarai Barat and six other districts in East Nusa Tenggara, with emergency shelter among the priority needs.
Hadi said BNPB was targeting completion of all 458 units in December, subject to coordination among the parties. He also said construction would resume on 16 November.
Floresa reported that contractors were financing construction themselves because the government had not provided an advance payment or guarantee. Payment was due only after a unit was fully built, with at least 10 units completed, and had passed inspection by the local government’s technical team.
Sources
Read next
More on this story

Flores & Beyond
Fire damages second floor of Manggarai Inspectorate office
A fire damaged the second floor of Manggarai’s Inspectorate office in Ruteng on 12 November, with no deaths reported and police investigating a suspec…
Most read in Flores & Beyond

Today’s top story

Related