Residents oppose geothermal land acquisition in Flores and Lembata
Residents in Poco Leok and Atadei oppose surrendering customary land for planned geothermal projects. Dialogue offers have not changed their position as land acquisition continues.
· 2 min read
Flores — Residents in Poco Leok and Atadei continued opposing the handover of customary land for planned geothermal projects on 19 November 2026, while the government, PLN and project financiers offered dialogue and land acquisition efforts continued, Floresa reported.
In Atadei, Lembata, residents blocked a land-acquisition socialisation team on 14 October 2026 at the Petun intersection on the main road to Atakore village, according to Floresa. Residents of Atakore had decided to reject the project during a meeting on 8 October 2024, citing concern about damage to Ina Kar, a customary site described in the report as a “natural kitchen”.
In Poco Leok, Manggarai, residents opposing the project said customary land, living space and ancestral heritage could not be surrendered. Floresa reported that the dispute also involved concerns about the effects of geothermal development observed in other areas.
Separate coverage by Betahita said residents from four customary villages—Gendang Lungar, Gendang Tere, Gendang Racang and Gendang Rebak—blocked company vehicles from entering Lingko Tanggong, customary land designated as a geothermal drilling site known as Wellpad D. Betahita reported that the blockade was the eighth such action and that residents planned to continue opposing land-marking, inventory and clarification activities.
Why it matters to readers
The dispute links renewable-energy development with customary-land rights in two destinations within the wider Flores travel region. The reports show that proposed geothermal projects are not only an energy question, but also concern access to land, community consent and culturally significant places.
Atadei is in Lembata, while Poco Leok is in Manggarai. A report from another local outlet said that dialogue offers from the government, PLN and project financiers had not changed the position of residents in either area.
The same report said land acquisition remained under way in Poco Leok and that an independent KfW team had recommended temporarily stopping the project. It also reported that, by March 2026, PLN had paid compensation to 280 landowners and controlled 549 parcels, with payment for 38 additional parcels expected to follow the acquisition process.
Floresa reported no final resolution to the opposition. Land acquisition efforts and dialogue therefore remain the immediate next steps described in the coverage.
Sources
Read next
More on this story

Tourism Business
PLN completes Ruteng Substation upgrade in Manggarai
PLN replaced the current transformer on the Bus 1 Bay Kopel at Ruteng Substation on 15 November 2026. The work was intended to support more stable ele…
Latest in Flores & Beyond

Related